File #: 19-429    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 3/15/2019 In control: Public Works
On agenda: 4/9/2019 Final action: 4/9/2019
Title: ADA Curb Ramp Improvements Project (Phase 1); Contract Number 325701
Attachments: 1. Staff Report, 2. Bid Results, 3. Request for Budget Transfer, 4. Proof of Publication.pdf
Previous Action/Referral: 22-439, 23-880, 23-509, 22-711, 24-176

To: Board of Supervisors

From: Public Works

Agenda Section: Consent

SUBJECT:
title
ADA Curb Ramp Improvements Project (Phase 1); Contract Number 325701
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and file the bid proposals received for the ADA Curb Ramp Improvements Project;
2. Award the contract to RAO Construction Co., Inc., for the total amount of $1,687,447.50;
3. Authorize the Chair of the Board to execute the project agreement upon submittal of the appropriate bonds and insurance; and
4. Direct the Auditor-Controller to establish a new contract account 1200321-0335 ADA Curb Ramp Improvements and transfer $500,000 from 1200321-2118 to the new contract account per the attached appropriation transfer.

Body
SOURCE OF FUNDING:
Humboldt County Road Fund (1200321)

DISCUSSION:
On Feb. 5, 2019, the Board of Supervisors authorized the Clerk of the Board to advertise the above-referenced project for bids. On March 12, 2019, the county received three bids for the project, and the results are attached.

The Department of Public Works recommends that the Board of Supervisors receive and file the bid proposals, award the contract, authorize execution of the project agreement, and set up the capital contract account.

FINANCIAL IMPACT:
This project is being funded by the Humboldt County Road Fund. The engineer's estimate for the construction contract is $1,899,877. Total project cost is estimated at $2,025,000. Due to budget constraints, only $500,000 can be transferred from budget line 1200321-2118 Professional & Special Services to 1200321-0335 ADA Curb Ramp Improvements in the current Fiscal Year (FY) 2018-2019. ADA Ramp construction is not expected to exceed this allocation for the remainder of the FY 18-19. The remaining $1,525,000 in construction costs will be included in FY 19-20 for Road Fund budget unit 1200321-0335 ADA Improvement Project. Therefore, this project will not impact the General Fund.

STRATE...

Click here for full text