File #: 23-880    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 6/14/2023 In control: Public Works
On agenda: 7/11/2023 Final action: 7/11/2023
Title: Bid Award Authorization for Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3)
Attachments: 1. Staff Report, 2. Bid Results for the Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3), 3. Construction Agreement for the Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3)
Previous Action/Referral: 19-109, 19-429, 20-1558, 22-439, 22-711, 23-509
To: Board of Supervisors

From: Public Works

Agenda Section: Consent

Vote Requirement: Majority

SUBJECT:
title
Bid Award Authorization for Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3)
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and file the bid proposal submitted for the Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3);
2. Award the attached project agreement to GR Sundberg, Inc., for the total amount of $1,436,631;
3. Authorize the Chair of the Board to execute the attached project agreement with GR Sundberg, Inc., upon submittal of the appropriate bonds and insurance; and
4. Authorize the Public Works Director to execute contract change orders up to the amount of $84,331.

Body
SOURCE OF FUNDING:
Road Fund (1200-321)
2020 Finance Plan

DISCUSSION:
On May 2, 2023, the Board of Supervisors authorized the Clerk of the Board to advertise the Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3) for bids. On June 6, 2023, the County of Humboldt received one (1) bid for the project, which is attached hereto as Attachment 1.

The Department of Public Works recommends that the Board of Supervisors receive and file the bid proposal submitted for the Americans with Disabilities Act Curb Ramp Improvements Project (Phase 3); award the attached project agreement to GR Sundberg, Inc., for the total amount of $1,436,631; authorize the Chair of the Board to execute the attached project agreement with GR Sundberg, Inc., upon submittal of the appropriate bonds and insurance; and authorize the Public Works Director to execute contract change orders up to the amount of $84,331.

FINANCIAL IMPACT:
Expenditures (Fund, Budget Unit)
FY23-24 Adopted
Budgeted Expenses (1200321-8940)
$1,436,631
Budgeted Expenses (1200321-1100)
$143,369
Total Expenditures
$1,580,000
Funding Sources (Fund, Budget Unit)
FY23-24 Adopted
2020 Finance Plan
$1,400,000
SB1 RMRA
$36...