File #: 23-1549    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 11/17/2023 In control: Public Works
On agenda: 12/12/2023 Final action: 12/12/2023
Title: Change Order and Project Contingency Authorization for Storm Damage Repairs to Panther Gap Road (4D010) Post Mile 0.50 (4/5 vote required)
Attachments: 1. Staff Report, 2. Change Order Number 5 to Contract Number 217387, 3. Change Order Number 7 to Contract Number 217387
Previous Action/Referral: 22-1609, 22-687, 22-678, 21-1792, 19-157

To: Board of Supervisors

From: Public Works

Agenda Section: Consent

Vote Requirement: 4/5th

SUBJECT:
title
Change Order and Project Contingency Authorization for Storm Damage Repairs to Panther Gap Road (4D010) Post Mile 0.50 (4/5 vote required)
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve, and authorize the Director of Public Works to execute, the attached change order number 5 to contract number 217387 for the total amount of $32,976.90 (4/5 Vote Required);
2. Approve, and authorize the Director of Public Works to execute, the attached change order number 7 to contract number 217387 for the total amount of $95,000 (4/5 Vote Required).
3. Approve additional project contingency funds in the amount of $500,000; and
4. Authorize the Director of Public Works to execute change orders up to the amount of $210,000.

Body
SOURCE OF FUNDING:
Humboldt County Road Fund (1200); Federal Emergency Management Agency; California Governor's Office of Emergency Services

DISCUSSION:
On June 7, 2022, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise Storm Damage Repair to Panther Gap Road (4D010) Post Mile 0.50 for bids and authorized the Director of Public Works to award the project agreement to the lowest responsive bidder following completion of the bidding process and to execute the project agreement with the lowest responsive bidder upon submittal of the appropriate bonds and insurance. On July 12, 2022, the County of Humboldt received six (6) bids for the project. The Director of Public Works awarded the contract to Wahlund Construction, Inc., the lowest responsive bidder, on July 14, 2022. The work consisted of excavation for new roadway, disposal of excess excavation materials, construction of gravel roadway, and installation of drainage systems, geosynthetic reinforcement, and erosion and sediment control items. The project restored local traffic on Panther Gap Road when field wor...