File #: 18-1660    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 12/17/2018 In control: County Administrative Office
On agenda: 1/8/2019 Final action: 1/8/2019
Title: Bid Authorization for Americans with Disabilities Act (ADA) Department of Justice (DOJ) Consent Decree Barrier Removal at A.W. Way Park, 36588 Mattole Road, Petrolia, California 95558
Attachments: 1. Staff Report, 2. Attachment 1 Architectural Plans for ADA improvements at AW Way Park, 3. Attachment 2 Specifications for ADA improvements at AW Way Park

To: Board of Supervisors

From: County Administrative Office

Agenda Section: Consent

SUBJECT:
title
Bid Authorization for Americans with Disabilities Act (ADA) Department of Justice (DOJ) Consent Decree Barrier Removal at A.W. Way Park, 36588 Mattole Road, Petrolia, California 95558
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and approve the plans and specifications for A.W. Way Park Americans with Disabilities Act (ADA) Project; and
2. Authorize the Clerk of the Board to advertise the above-referenced project, pursuant to Section 22037 of the California Public Contract Code, with bids to be open on February 12, 2019.

Body
SOURCE OF FUNDING:
ADA Internal Service Fund (3552)
ADA Trust (4491)


DISCUSSION:
On September 7, 2016, the county entered into a Consent Decree with the United States Department of Justice (DOJ) that required the commencement of the Humboldt County Americans with Disabilities Act Compliance Project. The purpose of the Humboldt County Americans with Disabilities Act Compliance Project is to bring all county-owned and leased facilities that provide programs, services and activities to the public into compliance with the ADA by September 07, 2019. The A.W. Way Park project is part of this compliance effort.

On June 5, 2018, the County of Humboldt entered into a consultant services agreement with The KPA Group to design ADA improvements at A.W. Way Park. The construction project will include ADA modifications as follows: providing one (1) accessible parking stall at the entry sign and fee station; providing two (2) accessible paved campsites with one (1) accessible parking stall at each campsite; replacing existing water spigot at entry sign with accessible drinking fountain; providing accessible paths of travel between (new) campsites, toilet rooms, (new) drinking fountain, and the fee/entry station.

The construction schedule is expected to be 60 calendar days and is antici...