To: Board of Supervisors
From: Public Works
Agenda Section: Consent
SUBJECT:
title
Bid Award Authorization for Storm Damage Repair to Briceland Thorne Road Post Mile 3.76
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and file the bid proposals submitted for Storm Damage Repair to Briceland Thorne Road Post Mile 3.76;
2. Award the project agreement to GR Wilcox Enterprises, Inc., for the total amount of $216,673.67;
3. Authorize the Chair of the Board to execute the project agreement upon submittal of the appropriate bonds and insurance; and
4. Authorize the Public Works Director to execute contract change orders up to the amount of $21,666.33.
Body
SOURCE OF FUNDING:
Road Fund (1200); Federal Emergency Management Agency; and California Governor’s Office of Emergency Services
DISCUSSION:
On May 10, 2022, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise Storm Damage Repair to Briceland Thorne Road Post Mile 3.76 for bids. On June 14, 2022, the county received three (3) bids for the project, which are attached hereto as Attachment 1.
The Department of Public Works recommends that the Board of Supervisors: 1) receive and file the bid proposals submitted for Storm Damage Repair to Briceland Thorne Road Post Mile 3.76; 2) award the attached project agreement to GR Wilcox Enterprises, Inc., for the total amount of $216,673.67; 3) authorize the Chair of the Board to execute the attached project agreement upon submittal of the appropriate bonds and insurance; and 4) authorize the Public Works Director to execute contract change orders up to the amount of $21,666.33.
FINANCIAL IMPACT:
Storm Damage Repair to Briceland Thorne Road Post Mile 3.76 is being funded by Federal Emergency Management Agency (FEMA) Disaster Funds (75%), the California Governor’s Office of Emergency Services (18.75%), and the Humboldt County Road Fund (6.25%). The contract bid amount is $216,673.67. The total project cost is estimated at $270,840. The Humboldt County Road Fund will be responsible for $16,927.50 of the total costs associated with the Briceland Thorne Road Post Mile 3.76 Storm Damage Repair Project.
Expenditure appropriations relating to completion of the Briceland Thorne Road Post Mile 3.76 Storm Damage Project are included in the proposed fiscal year 2022-23 budget for Road Fund budget, 1200-321-2118.
Projects are paid in arrears with anticipated funding coming from FEMA as mentioned above. The FY 2020-21 Annual Road Report, completed by the State of California, reflected an estimated negative fund balance of $5.9 million. This negative balance is due to the timing of FEMA reimbursements, which can take years for the county to receive repayment. The Department of Public Works utilizes other state and local funding, such as Regional Surface Transportation Program funds, for the 6.25% Humboldt County Road Fund match for FEMA projects.
STRATEGIC FRAMEWORK:
This action supports your Board’s Strategic Framework by providing for and maintaining infrastructure .
OTHER AGENCY INVOLVEMENT:
Federal Emergency Management Agency; California Governor’s Office of Emergency Services
ALTERNATIVES TO STAFF RECOMMENDATIONS:
The Board of Supervisors may choose not to award the project agreement for Storm Damage Repair to Briceland Thorne Road Post Mile 3.76. However, this alternative is not recommended because the project will restore the roadway to pre-disaster conditions using funds that would not otherwise be available to the County of Humboldt.
ATTACHMENTS:
1. Bid Results for Storm Damage Repair to Briceland Thorne Road Post Mile 3.76
2. Construction Agreement for Storm Damage Repair to Briceland Thorne Road Post Mile 3.76
PREVIOUS ACTION/REFERRAL:
Board Order No.: D-17
Meeting of: May 10, 2022
File No.: 22-501