Big River Farm, LLC; Conditional Use Permit and Special Permit
Record Number: PLN-11892-CUP (filed 12/27/2016)
Assessor Parcel Numbers (APN) 108-023-008
Ettersburg area
1.
A Conditional Use Permit (CUP) for Big River Farm, LLC to allow 22,000 square feet (SF) existing
outdoor cannabis cultivation on a 90-acre parcel, and a Special Permit to reduce the setback to BLM
public land. An approximately 1.1-acre area at the southern parcel line will be planted with trees under
the guidance and review of a Registered Professional Forester to increase the buffer to publicly owned
and managed lands, and to increase the habitat buffer. Cultivation occurs in six (6) greenhouses utilizing
light deprivation to achieve two harvest cycles. Propagation occurs onsite in a 2,190 SF ancillary
nursery. Irrigation water is sourced from a groundwater well which has been evaluated for connectivity
to surface waters, supplemented by rain catchment. The estimated annual irrigation water usage is
219,000-gal. (9.9 gal./SF/year). Water storage totals 86,600-gal. in hard tanks, and applicant has
secured grant funding to install an additional 50,000-gal. of storage tanks for a total of approximately
138,700-gal. Processing such as drying and curing will occur onsite in an existing 30’ x 40’ garage
attached to the 1,200 square foot residence, or in the existing 30’ x 40’ storage shed. All other
processing such as trimming and packaging will occur offsite at a licensed facility. Power for the
cultivation operation is provided by P.G.&E., and generators for emergency backup power. Five
employees are anticipated to meet operational needs during peak season.
That the Planning Commission:
Recommendation:
1. Adopt the resolution (Resolution 23-__), (Attachment 1) which does the
following:
a. Finds that the Planning Commission has considered the project specific
Addendum to the Mitigated Negative Declaration for the Commercial Medical
Marijuana Land Use Ordinance that was prepared for the Big River Farms, LLC
project); and
b. Finds that the proposed project complies with the General Plan and Zoning
Ordinance; and
c. Approves the Conditional Use Permit and Special Permit, subject to the
recommended conditions of approval (Attachment 1A)
OR
2. Adopt the alternative resolution (resolution 23-__), (Attachment 1E) which does
the following:
a. Finds the project exempt from environmental review pursuant to State CEQA
Guidelines Section 15270 (projects which are disapproved); and
b. Finds that the project has the potential to have a detrimental effect on the public
health, safety, and/or welfare in conflict with the General Plan and Zoning
Ordinance; and