File #: 24-240    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 2/14/2024 In control: Public Works
On agenda: 3/5/2024 Final action: 3/5/2024
Title: Measure Z - 2024 Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road and Redwood Drive Project
Attachments: 1. Staff Report, 2. 2024 Measure Z Plan Set_298100_2024-02-21_s-signed.pdf, 3. 2024 Measure Z Special Provisions_2024-02-21_s-signed.pdf, 4. NOE - 2024 Measure Z Paving Project.pdf
Previous Action/Referral: 24-34, 24-721

To: Board of Supervisors

From: Public Works

Agenda Section: Consent

Vote Requirement: Majority

SUBJECT:
title
Measure Z - 2024 Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road and Redwood Drive Project
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the attached plans and specifications for the Measure Z - 2024 Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road ad Redwood Drive Project;
2. Find that the project is exempt from environmental review pursuant to Section 15301 and 15302 of the California Environmental Quality Act (CEQA) Guidelines; and
3. Direct the Clerk of the Board to advertise the above-mentioned project as required by Section 22037 of the California Public Contract Code, with bids to be opened on Tuesday, April 2, 2024, at 2 p.m.

Body
SOURCE OF FUNDING:
Road Fund (1200), Measure Z

DISCUSSION:
The Measure Z - 2024 Project consists of repairing existing roadway by cold planning and replacing with hot mix asphalt on the travel lanes at nine locations throughout the county. These locations are Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road and Redwood Drive. Not included in the contract, but utilizing the same Measure Z 2024 funding is the Department of Public Works Road Maintenance Division's construction of the flat-car bridge at Little Dry Creek on the Mattole Road (F3C010) PM 22.60.

The Measure Z - 2024 Project mentioned herein falls under Categorical Exemption Class 1 (Existing Facilities) and Class 2 (Replacement or Reconstruction) under State CEQA Guidelines Section 15301 and 15302. This exemption applies to projects that are existing facilities and consist of replacement or reconstruction of existing structures and facilities where ...