Title: Bid Authorization for the Probation Building Fire Restoration, Project Number 170212F
Attachments: 1. Staff Report, 2. 170212F-ProbationFireBidDrawings_v2.pdf, 3. 170212F-ProbationFireBidSpecifications_v2b.pdf
To: Board of Supervisors

From: Public Works

Agenda Section: Consent

Vote Requirement: Majority

SUBJECT:
title
Bid Authorization for the Probation Building Fire Restoration, Project Number 170212F
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive the plans and specifications pertaining to the Probation Building Fire Restoration Construction Project, Project Number 170212F
2. Authorize the Clerk of the Board to advertise the Probation Building Fire Restoration Construction Project, pursuant to Section 22037 of the California Public Contract Code on June 13, 2023, with bids to be opened on July 11, 2023 at 2:00 PM

Body
SOURCE OF FUNDING:
Liability Fund (3524)

DISCUSSION:
The Juvenile Hall Replacement Project (Project #170212) approved for construction by your Board on August 16, 2016, included two phases. Phase 1 provided for the construction of the new Juvenile Hall facility located adjacent to the original Juvenile Hall Building. Phase 2 involved the demolition of the old Juvenile Hall facility and included the engineered seismic restoration to the existing Probation Administration Building, and which had previously shared structural elements and foundations and other building systems with the old Juvenile Hall building.

On October 21, 2021, during phase 2 renovation work at the existing Probation Facility, a fire occurred at the interior of the building, affecting significant portions of the building which suffered extensive fire, smoke, water and other damages throughout the interior and parts of the exterior. Extensive post-fire investigation and cleanup efforts forced the county to evacuate the facility and halt previous renovation work in order to perform hazardous material removal including asbestos and additionally so that restoration planning efforts could proceed.

Pre-construction planning efforts involved the removal of smoke, water, and fire damaged interior surfaces, as well as removal of all identif...