To: Board of Supervisors
From: Probation
Agenda Section: Consent
Vote Requirement: 4/5th
SUBJECT:
title
Supplemental Budget for Probation, Juvenile Hall Budget Unit 234, for the Replacement of HVAC Units on the Regional Facility (4/5ths Vote Required)
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the attached supplemental budget for Probation Juvenile Hall, budget unit 234 (4/5 vote required);
2. Approve the establishment of a fixed asset line in excess of $10,000 in 1100-234-8428.
Body
SOURCE OF FUNDING:
Included in the 2022-23 California Governor's Budget is a County Operated Juvenile Facility Grant Program. This funding is residing in Probation trust account 3782 and will be utilized to offset the difference between the total project cost and the American Rescue Plan Act (ARPA) funding available.
DISCUSSION:
HVAC units for the Probation Department's Regional Facility have needed replacement for many years. Probation worked with Public Works and budgeted for their replacement back in FY 2015-16 and the project never took place. Probation closed the Regional Facility and absorbed the New Horizons program into the newly constructed Juvenile Hall in FY 2020-21. The building is currently housing the Probation Department's Juvenile Division and Administration while 2002 Harrison is under construction due to a structural fire in October of 2021. Once displaced staff are able to return to their offices at 2002 Harrison Avenue, the Probation Department hopes to use the Regional Facility as additional programing space for youth in the Juvenile Hall.
This agenda item is requesting a transfer of $115,000 from Probation Trust 3782 to supplement Probation's Juvenile Hall Budget and provide required funding for the HVAC replacement project.
FINANCIAL IMPACT:
Expenditures (1100-234-8428)
FY22-23
FY23-24 Projected
FY24-25 Projected
Budgeted Expenses
Additional Appropriation Requested
115,000
Total Expenditu...