Title: Bid Award Authorization for Storm Damage Repair to Elk Creek Road (C6D060) at Post Mile 0.95-2.42
Attachments: 1. Staff Report, 2. Bid Results for Storm Damage Repair to Elk Creek Road at Post Mile 0.95-2.42, 3. Construction Agreement for Storm Damage Repair to Elk Creek Road at Post Mile 0.95-2.42
Previous Action/Referral: 22-502

To: Board of Supervisors

From: Public Works

Agenda Section: Consent

SUBJECT:
title
Bid Award Authorization for Storm Damage Repair to Elk Creek Road (C6D060) at Post Mile 0.95-2.42
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and file the bid proposals submitted for Storm Damage Repair to Elk Creek Road at Post Mile 0.95-2.42;
2. Award the project agreement to Van Meter Logging, Inc., for the total amount of $2,388,398;
3. Authorize the Chair of the Board to execute the project agreement upon submittal of the appropriate bonds and insurance; and
4. Authorize the Public Works Director to execute contract change orders up to the amount of $131,920.

Body
SOURCE OF FUNDING:
Humboldt County Road Fund (1200); Federal Highway Administration Emergency Relief Funds

DISCUSSION:
On Sept. 20, 2022, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise Storm Damage Repair to Elk Creek Road at Post Mile 0.95-2.42 for bids. On Oct. 25, 2022, the County of Humboldt received four (4) bids for the project, which are attached hereto as Attachment 1.

The Department of Public Works recommends that the Board of Supervisors: receive and file the bid proposals submitted for Storm Damage Repair to Elk Creek Road at Post Mile 0.95-2.42; award the attached project agreement to Van Meter Logging, Inc., for the total amount of $2,388,398; authorize the Chair of the Board to execute the attached project agreement upon submittal of the appropriate bonds and insurance; and authorize the Public Works Director to execute contract change orders up to the amount of $131,920.

FINANCIAL IMPACT:
Storm Damage Repair to Elk Creek Road at Post Mile 0.95-2.42 is being funded by Federal Highway Administration (FHWA) Emergency Relief Funds (88.53%) and the Humboldt County Road Fund (11.47%). The contract bid amount is $2,388,398. The total project cost is estimated at $2,985,500. The Humboldt County Road Fund wil...