File #: 22-574    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 4/27/2022 In control: Public Works
On agenda: 5/24/2022 Final action: 5/24/2022
Title: Bid Award Authorization for the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project
Attachments: 1. Staff Report, 2. Construction Agreement for the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project, 3. Bid Results for the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project, 4. Executed Contract Agreement - 321617.pdf
Previous Action/Referral: 22-276, 22-1464
To: Board of Supervisors

From: Public Works

Agenda Section: Consent

SUBJECT:
title
Bid Award Authorization for the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and file the bid proposals submitted for the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project;
2. Award the attached project agreement to Kernen Construction for the total amount of $259,999.84;
3. Authorize the Chair of the Board to execute the attached project agreement upon submittal of the appropriate bonds and insurance; and
4. Authorize the Public Works Director to execute contract change orders up to the amount of $25,500.

Body
SOURCE OF FUNDING:
Road Fund (1200); California Transportation Improvement Program

DISCUSSION:
On March 22, 2022, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project for bids. On April 26, 2022, the County of Humboldt received six (6) bids for the project, which are attached hereto as Attachment 1.

The Department of Public Works recommends that the Board of Supervisors: receive and file the bid proposals submitted for the Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project; award the attached project agreement to Kernen Construction for the total amount of $259,999.84; authorize the Chair of the Board to execute the attached project agreement upon submittal of the appropriate bonds and insurance; and authorize the Public Works Director to execute contract change orders up to the amount of $25,500.

FINANCIAL IMPACT:
The Central Avenue (4L800) Post Mile 0.00-0.30 Shoulder Widening Project is being funded by California Department of Transportation's State Transportation Improvement Program (100%). The contract bid amount is $259,999.84. The total project cost is estimated at $299,000. The Humboldt County Ro...

Click here for full text