File #: 20-1569    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 12/2/2020 In control: County Administrative Office
On agenda: 1/12/2021 Final action: 1/12/2021
Title: Carry Forward Budget Adjustment and Supplemental Budget Request (4/5 Vote Required)
Attachments: 1. Staff Report, 2. DGI PROPOSAL-25305.pdf, 3. Supplemental Budget 20-1569.pdf

To: Board of Supervisors

From: County Administrative Office

Agenda Section: Consent

SUBJECT:
title
Carry Forward Budget Adjustment and Supplemental Budget Request (4/5 Vote Required)
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the attached supplemental budget in fund 3550 budget unit 118 Information Technology to carry forward unexpended funds of $42,832 for approved expenses in Fiscal Year (FY) 2019-20 into FY 2020-21 and $126,265 for the Courthouse network switch replacements. (4/5 Vote Required)

Body
SOURCE OF FUNDING:
Information Technology Fund

DISCUSSION:
In FY 2019-20 funding was allocated for the security system door lock replacement and upgrade in the Humboldt County Courthouse. The project was not completed in FY 2019-20 and allocations were unable to be expended as budgeted. It is requested that your Board carry forward the remainder of the approved allocation of $42,832 into FY 2020-21 in order to pay for this project.

In addition, the current network infrastructure that provides telephony and network access to multiple departments in the Courthouse, is outdated and insufficient to meet current needs. This equipment has reached its end of life and is at high risk of catastrophic systems failure. Installation of new equipment is required to ensure all departments in the courthouse have adequate and dependable telephone and network access. Accordingly, staff recommend your Board approve a supplemental budget request totaling $126,265 for the purchase of new equipment. Funding for this request is available through fund balance.

FINANCIAL IMPACT:
The approval of the budget adjustments will carry forward $42,832 in funding allocated in FY 2019-20 into FY 2020-21 and approve the supplemental budget of $126,265 from the Information Technology Fund in FY 2020-21. There is no impact to the General Fund.

STRATEGIC FRAMEWORK:
This action supports your Board's Strategic Framework by providing for and...