File #: 20-851    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 7/1/2020 In control: Public Works
On agenda: 7/14/2020 Final action: 7/14/2020
Title: Preventive Maintenance to Honeydew Bridge (4C-055) on Mattole Road (3D010) Post Mile 0.00 RECOMMENDATION(S):
Attachments: 1. Staff Report, 2. Honeydew BPMP_Plans.pdf, 3. Honeydew BPMP_Special Provisions_r2.pdf
Previous Action/Referral: 17-2218, 17-2109, 17-2474, 23-489
To: Board of Supervisors

From: Public Works

Agenda Section: Consent

SUBJECT:
title
Preventive Maintenance to Honeydew Bridge (4C-055) on Mattole Road (3D010) Post Mile 0.00

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the attached plans and specifications for the Honeydew Bridge (4C-055) Preventive Maintenance Project on Mattole Road (3D010) Post Mile 0.00;
2. Direct the Clerk of the Board to advertise the above-mentioned project as required by Section 22037 of the California Public Contract Code, with bids to be opened on Tuesday, August 11, 2020, at 2:00 p.m.;
3. Authorize the Humboldt County Public Works Director to award the above-mentioned project to the lowest responsive bidder following completion of the bidding process; and
4. Authorize the Humboldt County Public Works Director to execute a project agreement that is substantially similar to the construction agreement included in the attached plans and specifications the lowest responsive bidder upon submittal of the appropriate bonds and insurance.

Body
SOURCE OF FUNDING:
Road Fund (1200); Federal Highway Administration's Bridge Preventive Maintenance Program

DISCUSSION:
On February 14, 2017, the Humboldt County Department of Public Works ("Public Works") advertised for construction of the Bridge Preventive Maintenance Program Projects at North Fork Mad River Bridge (4C-026) on Maple Creek Road (5L100) Post Mile 1.32 and Honeydew Bridge (4C-055) on Mattole Road (3D010) Post Mile 0.00. Public Works received one (1) bid proposal and the bid amount was significantly higher than the engineer's cost estimate. As a result, the Board of Supervisors rejected the bid on October 17, 2017.

On December 7, 2019, Public Works issued task order number DPW2018-007-T02 to Quincy Engineering Inc. to analyze the design strategy and prepare plans, specifications and cost estimate for re-bidding and construction of the above-referenced bridge preventive maintenance pro...