To: Board of Supervisors
From: Public Works
Agenda Section: Consent
SUBJECT:
title
Right of Way Contract (Temporary Construction Easement) - State Highway 101 (4th Street) Improvement Project - 826 4th Street, Eureka (Courthouse)
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the Right of Way Contract for a Temporary Construction Easement (TCE) to perform curb and driveway improvements along the entrance to 826 4th Street;
2. Authorize the Chair of the Board to sign two originals of the TCE;
3. Authorize the Public Works Director to execute a quitclaim document for the TCE after completion of the California Department of Transportation (Caltrans) project; and
4. Direct the Clerk of the Board to return one executed original of the TCE to Public Works - Real Property - for transmittal to Caltrans.
Body
SOURCE OF FUNDING:
California Department of Transportation (Caltrans)
DISCUSSION:
Caltrans has a project to improve the safety and operation of State Route 101 (4th Street), by constructing Accessibility Disability Act (ADA) regulation intersections from Y Street through Commercial Street. Work will consist of installing bulb outs at cross street intersections, and modification of curbs and driveways to meet the grade requirements of ADA. All construction work will be within the 4th Street Right of Way of Caltrans.
The driveway at 826 4th Street is within the Caltrans Right Way and requires replacement. It is used by the Sheriff Department for egress from the Courthouse. The driveway is approximately 12 feet deep and is sloped from the street to the property line. The slope of the driveway is not in compliance with ADA regulations for sidewalk purposes. A wheel chair occupant, for example, cannot safely maneuver across the sloped driveway. To remedy this situation, the existing driveway will be replaced with a new driveway / sidewalk, consisting of the first 6 feet to the property line being flat. The new flat area will therefore meet the sidewalk grade requirements of ADA (Attachment 3 - Sketch).
Caltrans is requesting the county to execute a TCE consisting of an 11-foot by 58-foot strip of land behind the sidewalk, the location of which is shown in Attachment 1 - Right of Way Appraisal Map. Caltrans will need this strip to allow workers to safely remove the old driveway and install the new driveway while staying outside of the traveled way. Consideration from Caltrans to use this strip will be $3,900 made payable to the county as described in Attachment 2 - Valuation Summary Statement.
A review with the Sheriff’s Department indicates no issues with the project and the TCE, provided egress for one half of the driveway be open during construction. Construction is planned for the Spring of 2019 and will take approximately 1 week to accomplish. Notification will be made to the Sheriff’s Department prior to commencement of work. After completion, the county will request Caltrans to quitclaim the TCE so as to prevent further Caltrans work after completion of construction.
FINANCIAL IMPACT:
The county will receive funding in the amount of $3,900 for the Temporary Construction Easement.
STRATEGIC FRAMEWORK:
This action supports your Board’s Strategic Framework by creating opportunities for improved safety and health.
OTHER AGENCY INVOLVEMENT:
California Department of Transportation
ALTERNATIVES TO STAFF RECOMMENDATIONS:
The Board could choose not to approve the TCE, however this is not recommended. Not approving the TCE will prevent Caltrans from improving the driveway, and will therefore delay their project and force an Eminent Domain process to begin, thus creating negative publicity for the County.
ATTACHMENTS:
Right of Way Contract
Attachment 1 - Right of Way Appraisal Map
Attachment 2 - Valuation Summary Statement
Attachment 3 - Sketch
PREVIOUS ACTION/REFERRAL:
Board Order No.: N/A
Meeting of: N/A