File #: 19-211    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 2/5/2019 In control: Public Works
On agenda: 2/19/2019 Final action: 2/19/2019
Title: Request for Budget Transfer/Adjustment in Roads Engineering (1200321)
Attachments: 1. Staff Report, 2. 321 Request for Budget Transfer

 

To:                                                               Board of Supervisors

 

From:                                          Public Works                                          

 

Agenda Section:                     Consent                                                               

 

SUBJECT:

title

Request for Budget Transfer/Adjustment in Roads Engineering (1200321)

end

 

RECOMMENDATION(S):

Recommendation

That the Board of Supervisors:

1.                     Approve the attached Budget Transfer/Adjustment in the amount of $1,000,000 for the Roads-Engineering Division to continue funding the Williams Creek Bridge Replacement.

 

Body

SOURCE OF FUNDING                     

Roads Engineering (1200321)

 

DISCUSSION:

In Fiscal Year 2017-18 the Engineering Department allocated $2,319,819 in funding for the Williams Creek Bridge Replacement under 1200321-0330. The project intended to span multiple years and its total construction allocation would not be expended in the 2017-18 fiscal year. Due to budget constraints, funding in the amount of $687,678 was temporarily reallocated from 1200321-0330 Williams Creek Bridge Replacement to Dinner Creek Culvert 1200321-0331.

 

Initially, when the project was created, consultant costs were not factored into the total estimated expenditure. The attached budget transfer request reallocates the $687,678 in funding from 1200321-2118 Professional Services back to 1200321-0330 Williams Creek Bridge, as well as an additional $312,322 for consultant, administration and construction costs.

 

FINANCIAL IMPACT:

The request, if granted, will transfer $1,000,000 from 1200321-2118 Professional Services, to 1200321-0330 Williams Creek Bridge Replacement. There is no impact to the General Fund.

 

STRATEGIC FRAMEWORK:

This action supports your Board’s Strategic Framework by providing for and maintaining infrastructure .

 

OTHER AGENCY INVOLVEMENT:                     

None

 

ALTERNATIVES TO STAFF RECOMMENDATIONS:                     

The Board could choose not to approve the Request for Budget Transfer/Adjustment. This is not recommended because the construction project is ongoing and the costs have been incurred. 

 

ATTACHMENTS:                     

Request for Budget Transfer Adjustment

 

PREVIOUS ACTION/REFERRAL:

Board Order No.: C21 / C21                     

Meeting of: Feb. 27, 2018 / May 8, 2018

File No.: N/A