File #: 16-0230    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 2/17/2016 In control: Public Works
On agenda: 2/23/2016 Final action: 2/23/2016
Title: Construction of Red Cap Road (8Q100) P.M. 0.00 to 0.30 (Phase 1); Project No.: RPSTPLE-5904(128); Contract No.: 321606
Attachments: 1. Construction of Red Cap Road.pdf

Title

Construction of Red Cap Road (8Q100) P.M. 0.00 to 0.30 (Phase 1); Project No.: RPSTPLE-5904(128); Contract No.: 321606

 

Recommendation

That the Board of Supervisors authorize the Director of Public Works to sign Contract Change Orders Number 2, 3 and 4 for the total amount of $45,706.58; and direct the Auditor-Controller to transfer $40,427.58 to 1200321-0313 per the attached appropriation transfer.