File #: 21-1775    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 11/29/2021 In control: Public Works
On agenda: 12/14/2021 Final action: 12/14/2021
Title: Acquisition of Interest in Real Property (Assessor Parcel No. 501-241-031, 501-241-030, 501-241-033, 017-081-001, 404-141-004) for the Humboldt Bay Trail South Project
Attachments: 1. Staff Report, 2. Attachment 1 - overview maps, 3. Attachment 2 - Bracut PSA and TCE final 11-29-2021, 4. Attachment 3 - PSA Humboldt Bay Trail Brainard CRC signed, 5. Attachment 4 - affidavit

To: Board of Supervisors

From: Public Works

Agenda Section: Public Hearing

SUBJECT:
title
Acquisition of Interest in Real Property (Assessor Parcel No. 501-241-031, 501-241-030, 501-241-033, 017-081-001, 404-141-004) for the Humboldt Bay Trail South Project
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Open the public hearing;
2. Receive the staff report and comments from the public;
3. Close the public hearing;
4. Find that Notice of Intention to acquire interest in real property to provide right-of-way for the Humboldt Bay Trail South Project was given pursuant to Government Code section 25350;
5. Approve the acquisition of real property designated with Assessor Parcel No. 501-241-031 and Assessor Parcel No. 501-241-030;
6. Approve the acquisition of a temporary construction easement on a portion of Assessor Parcel No. 501-241-033;
7. Approve the acquisition of permanent and temporary easements on portions of Assessor Parcel No. 017-081-001 and Assessor Parcel No. 404-141-004;
8. Approve, and authorize the Public Works Director to sign, the attached Purchase and Sale Agreements and associated deeds (and revisions or amendments with non-substantial changes); and
9. Appoint the Public Works Director, or the Deputy-Director for Environmental Services, to negotiate and execute documents reasonably necessary to complete the acquisitions.

Body
SOURCE OF FUNDING:
Bicycles & Trailways Program (1710)

DISCUSSION:
Humboldt County is implementing the Humboldt Bay Trail South Project ("Project") which would expand the Humboldt Bay Trail by four and a quarter (4.25) miles and complete the trail connection between Eureka and Arcata. The primary purpose of the Project is to improve safety and connectivity for non-motorized and motorized travelers and enhance public access to Humboldt Bay. The Project would provide significant advancement in active transportation, recreation, and coastal access opportunities in the Humboldt...

Click here for full text