SUBJECT:
title
Third Amendments to the Consultant Services Agreements with Quincy Engineering, Inc., as Assigned to Consor North America, Inc., Regarding the Provision of Design Engineering and Environmental Services for the Holmes-Larabee and McCann Bridge Projects
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve, and authorize the Chair of the Board to execute, the attached third amendment to the consultant services agreement with Quincy Engineering, Inc., as assigned to Consor North America, Inc., regarding the provision of design engineering and environmental services for the Holmes-Larabee Bridge Project [Contract Number 594171]; and
2. Approve, and authorize the Chair of the Board to execute, the attached third amendment to the consultant services agreement with Quincy Engineering, Inc., as assigned to Consor North America, Inc., regarding the provision of design engineering and environmental services for the McCann Bridge Project [Contract Number 594172]; and
3. Direct the Clerk of the Board to return one (1) fully executed original copy of the attached third amendments to the consultant services agreements with Quincy Engineering, Inc., as assigned to Consor North America, Inc., to the Engineering Division of the Department of Public Works for further processing.
Body
STRATEGIC PLAN:
The recommended actions support the following areas of the Board of Supervisors' Strategic Plan:
Core Roles: Provide for and maintain infrastructure
Area of Focus: Safe & Healthy Communities
Strategic Plan Category: 1007 - Improve the transportation network to be multi-model, safe, sustainable and equitable
DISCUSSION:
On March 14, 2017, the Humboldt County Department of Public Works ("Public Works") issued a Request for Qualifications Number DWP2017-002 ("RFQ No. DWP2017-002") for the purpose of selecting a qualified consultant t...
Click here for full text