File #: 23-793    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 6/1/2023 In control: County Administrative Office
On agenda: 7/18/2023 Final action: 7/18/2023
Title: Final Acceptance for the Humboldt County Correctional Facility Accessibility Improvement Project, Project Number 2019-102 (4/5 Vote Required)
Attachments: 1. Staff Report, 2. 1. Notice of Completion, 3. Supplemental Budget
To: Board of Supervisors

From: County Administrative Office

Agenda Section: Consent

Vote Requirement: 4/5th

SUBJECT:
title
Final Acceptance for the Humboldt County Correctional Facility Accessibility Improvement Project, Project Number 2019-102 (4/5 Vote Required)
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Accept, and authorize the Humboldt County Purchasing Agent to execute and file the attached Notice of Completion regarding, the Humboldt County Correctional Facility Accessibility Improvement Project (4/5 vote required);
2. Approve the attached Supplemental Budget in the amount of Seventy-Three Thousand Five Hundred Six Dollars and Forty-Two Cents ($73,506.42) for ADA Internal Service Fund budget unit (3552-152) (4/5 vote required); and
3. Direct the Clerk of the Board to provide the County Administrative Office - ADA Compliance Team with one (1) fully executed certified copy of the Board Order related to this item.

Body
SOURCE OF FUNDING:
ADA Internal Service Fund (3552)

DISCUSSION:
On December 8, 2020, the Humboldt County Board of Supervisors ("Board") authorized staff to award the Humboldt County Correctional Facility Accessibility Improvement Project to Adams Commercial General Contracting, Inc. ("ACGC") of Eureka, California for the base bid amount of One Million One Hundred Ten Thousand Seven Hundred Fifty-Six Dollars ($1,110,756.00). The construction project renovated and improved accessibility features for the designated accessible showers, lavatories, toilets and handrails in each of the remaining housing units, replaced the second-floor inmate restroom door and renovated of one (1) of the staff restrooms on the second floor as well as remediated other miscellaneous barriers to access. Non-accessible toilets, lavatories, urinals and showers were excluded from the project design and scope as the project was limited to removing barriers to access with the ADA accessible fixtures in the dormitories. Non-...