To: Board of Supervisors
From: County Administrative Office
Agenda Section: Consent
Vote Requirement: 4/5th
SUBJECT:
title
Final Acceptance for the Humboldt County Correctional Facility Accessibility Improvement Project, Project Number 2019-102 (4/5 Vote Required)
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Accept, and authorize the Humboldt County Purchasing Agent to execute and file the attached Notice of Completion regarding, the Humboldt County Correctional Facility Accessibility Improvement Project (4/5 vote required);
2. Approve the attached Supplemental Budget in the amount of Seventy-Three Thousand Five Hundred Six Dollars and Forty-Two Cents ($73,506.42) for ADA Internal Service Fund budget unit (3552-152) (4/5 vote required); and
3. Direct the Clerk of the Board to provide the County Administrative Office - ADA Compliance Team with one (1) fully executed certified copy of the Board Order related to this item.
Body
SOURCE OF FUNDING:
ADA Internal Service Fund (3552)
DISCUSSION:
On December 8, 2020, the Humboldt County Board of Supervisors ("Board") authorized staff to award the Humboldt County Correctional Facility Accessibility Improvement Project to Adams Commercial General Contracting, Inc. ("ACGC") of Eureka, California for the base bid amount of One Million One Hundred Ten Thousand Seven Hundred Fifty-Six Dollars ($1,110,756.00). The construction project renovated and improved accessibility features for the designated accessible showers, lavatories, toilets and handrails in each of the remaining housing units, replaced the second-floor inmate restroom door and renovated of one (1) of the staff restrooms on the second floor as well as remediated other miscellaneous barriers to access. Non-accessible toilets, lavatories, urinals and showers were excluded from the project design and scope as the project was limited to removing barriers to access with the ADA accessible fixtures in the dormitories. Non-...
Click here for full text