File #: 23-478    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 3/30/2023 In control: Planning and Building
On agenda: 5/2/2023 Final action: 5/2/2023
Title: Moore Lot Line Adjustment and Joint Timber Management Plan (4/5 Vote Required) APNs: 205-011-037, 205-081-012, 205-011-007, 205-031-005 Record Number: PLN-2022-18031
Sponsors: Planning and Building
Attachments: 1. Staff Report, 2. Attachment 1 - Draft Resolution, 3. Attachment 1A - Conditions of Approval, 4. Attachment 1B - Plot Plan for Lot Line Adjustment, 5. Attachment 2 - Location Map, 6. Attachment 3 - Draft Declaration of Covenants, Conditions and Restrictions Implementing Joint Timber Management Plan, 7. Attachment 4 - Joint Timber Management Plan, 8. Attachment 5 - Forestry Review Committee Draft Minutes, February 8, 2023, 9. Attachment 6 - Referral Agency Comments, 10. Resolution No. 23-55.pdf

To: Board of Supervisors

From: Planning and Building Department

Agenda Section: Consent

Vote Requirement: 4/5th

SUBJECT:
title
Moore Lot Line Adjustment and Joint Timber Management Plan (4/5 Vote Required)
APNs: 205-011-037, 205-081-012, 205-011-007, 205-031-005
Record Number: PLN-2022-18031
end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Adopt the resolution (Attachment 1) to
a. Find the project exempt from environmental review pursuant to Sections 15061(b)(3) and 15305(a) of the State CEQA Guidelines and make all the required findings to approve the Lot Line Adjustment; and
2. Approve (4/5 Vote Required) the Joint Timber Management Plan (Attachment 4) prepared pursuant to Section 51119.5 of the California Government Code (C.G.C.); and
3. Direct the Planning Division staff to record the Declaration with the JTMP and the Notices of Lot Line Adjustment and Certificate of Subdivision Compliance; and
4. Direct the Clerk of the Board to give notice of the decision to owners, the County Assessor's Office and any other interested party.

Body
SOURCE OF FUNDING:
Applicant fees. (1100277)

DISCUSSION:
Moore Lot Line Adjustment and Joint Timber Management Plan (4/5 vote required)
APNs: 205-011-037, 205-081-012, 205-011-007, 205-031-005
Record Number: PLN-2022-18031

A Lot Line Adjustment (LLA) between two parcels of approximately 169 acres and 43 acres resulting in two parcels of 81 and 131 acres to provide more logical management units for both timber and grazing. A Joint Timber Management Plan (JTMP) is required due to the resultant parcels containing less than 160 acres of Timberland Production Zone (TPZ). One parcel is developed with a single-family residence and a barn, and the other parcel is vacant.

Project Location: The project is located in the Rio Dell area, on the north and south sides of Blue Slide Road, approximately at the intersection of Peppertree Lane and Blue Slide Road, on the properties known as 10365 and 1...

Click here for full text