To: Board of Supervisors
From: Public Works
Agenda Section: Consent
Vote Requirement: 4/5th
SUBJECT:title
Change Order 3.0 for the Information Technology Network Operations Center Heating, Ventilation and Air Conditioning Replacement Project, Project Number 162830 and Supplemental Budget Request in the amount of Forty-Two Thousand Seven Hundred Nine Dollars ($42,709.00) for Public Works Capital Projects Budget Unit 3562-170 (4/5 Vote Required)end
RECOMMENDATION(S):Recommendation
That the Board of Supervisors:
1. Accept the work of BESC, Inc., doing business as California Heating, as substantially complete for the Information Technology Network Operations Center Heating, Ventilation and Air Conditioning Replacement Project; and
2. Authorize the Public Works Director, or a designee thereof, to file the Notice of Completion for the Information Technology Network Operations Center Heating, Ventilation and Air Conditioning Replacement Project as required; and
3. Approve, and authorize the Public Works Director, or a designee thereof, to execute, Change Order 3.0 with BESC, Inc., doing business as California Heating, for a total cost increase of Forty-Two Thousand Seven Hundred Nine Dollars ($42,709.00) and a time extension of two hundred ten (210) days (4/5 Vote Required); and
4. Approve the attached supplemental budget in the amount of Forty-Two Thousand Seven Hundred Nine Dollars ($42,709.00) from Deferred Maintenance Fund to Public Works Capital Projects budget unit 3562-170 (4/5 Vote Required).
Body
STRATEGIC PLAN:
The recommended actions support the following areas of the Board of Supervisors' Strategic Plan:
Area of Focus: Workforce & Operational Excellence
Strategic Plan Category: 3002 - Invest in county facilities
DISCUSSION:
On November 29, 2022, the Board approved award of the Information Technology Network Operations Center Heating, Ventilation and Air Conditioning Replacement Project, Project Number 162830, to the lowest responsible an...
Click here for full text