To: Board of Supervisors
From: Public Works
Agenda Section: Consent
Vote Requirement: 4/5th
SUBJECT:
title
Accept Completed Contract for Measure Z - Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road and Redwood Drive Project and Ratify Execution of Contract Change Order Number 2 and Contract Change Order Number 3 (4/5 Vote Required)
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the attached appropriation transfer to increase a fixed asset line in fiscal year 2024-2025 for the Measure Z - Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road and Redwood Drive Project in the amount of Twenty-Three Thousand Three Hundred Nine Dollars ($23,309.00) in Public Works - Engineering budget unit 1200-321 (4/5th Vote Required); and
2. Approve, and ratify the Director of Public Works' execution of, Contract Change Order Number 2 for the total amount of Twenty-Four Thousand Four Hundred Fifty-Three Dollars and Three Cents ($24,453.03) (4/5th Vote Required); and
3. Approve, and ratify the Director of Public Works' execution of, Contract Change Order Number 3 for the total amount of Twenty-Three Thousand Three Hundred Eight Dollars and Ninety-Two Cents ($23,308.92) (4/5th Vote Required); and
4. Accept the completed contract, including all approved change orders, between Wahlund Construction, Inc., and Humboldt County for construction of Measure Z - Humboldt Hill Road, Ridgewood Drive, Eel River Drive, New Navy Base Road, Fieldbrook Road, Murray Road, Salmon Creek Road, Thomas Road, and Redwood Drive Project; and
5. Approve the final claim for payment, to be submitted by the Department of Public Works to the Auditor-Controller's Office, in the amount of One Hundred Fifty Dollars ($150.00), which will bring the total amount paid to 100% of the contract; and
6. Direct the...
Click here for full text