To: Board of Supervisors
From: Public Works
Agenda Section: Consent
SUBJECT:
title
Bid Award Authorization for Storm Damage Repair to Mattole Road (F3C010) Post Miles 40.98, 42.76 and 43.62
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Receive and file the bid proposals submitted for the Mattole Road (F3C010) Post Miles 40.98, 42.76 and 43.62 Storm Damage Repair Project;
2. Award the attached project agreement to Wahlund Construction, Inc., for the total amount of Nine Hundred Twenty-Eight Thousand Fifty-Six Dollars and Seventy Cents ($928,056.70); and
3. Authorize the Chair of the Board to execute the attached project agreement with Wahlund Construction, Inc. upon submittal of the appropriate bonds and insurance.
Body
SOURCE OF FUNDING:
Road Fund (1200); Federal Highway Administration Emergency Relief Funds
DISCUSSION:
On Feb. 9, 2021, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise the Mattole Road (F3C010) Post Miles 40.98, 42.76 and 43.62 Storm Damage Repair Project for bids. On March 16, 2021, the County of Humboldt received four bids for the project. The bid results are attached hereto as Attachment 1.
The Department of Public Works recommends that the Board of Supervisors receive and file the bid proposals submitted for the Mattole Road (F3C010) Post Miles 40.98, 42.76 and 43.62 Storm Damage Repair Project. Staff also recommends that the attached project agreement be awarded to Wahlund Construction, Inc., for the total amount of $928,056.70 and that the Chair of the Board be authorized to execute the attached project agreement with Wahlund Construction, Inc. upon submittal of the appropriate bonds and insurance.
FINANCIAL IMPACT:
The Mattole Road (F3C010) Post Miles 40.98, 42.76 and 43.62 Storm Damage Repair Project is being funded by Federal Highway Administration Emergency Relief Funds (88.53%) and the Humboldt County Road Fund (11.47%). The contract bid amount is N...
Click here for full text