Title: Construction of Storm Damage Repairs on Alderpoint Road (F6B165) at PM 42.00-42.46; Project No.: ER-4400(050); Contract No.: 206418
Attachments: 1. Storm Damage Repairs on Alderpoint Road.pdf
Title
Construction of Storm Damage Repairs on Alderpoint Road (F6B165) at PM 42.00-42.46; Project No.: ER-4400(050); Contract No.: 206418
 
Recommendation
That the Board of Supervisors receive and file the bids for Construction of Storm Damage Repairs on Alderpoint Road at PM 42.00-42.46; award the contract to G.R. Wilcox Enterprises, Inc. for the total amount of $729,472.80; authorize the Chairman to execute the project agreement upon submittal of the appropriate bonds and insurance; and direct the Auditor-Controller to establish a new contract account 1200321 -0317 and transfer $765,947.00 to the account per the attached appropriation transfer.