To: Board of Supervisors
From: Public Works
Agenda Section: Consent
SUBJECT:
title
Accept Completed Contracts for Storm Damage Repair to Mattole Road (F3D010) Post Miles 4.40, 5.10, 9.00, and 11.05-11.29
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Ratify the Director of Public Works to sign Contract Change Order Number 2-S1 for the total amount of $20,850.90 for Post Mile 4.40;
2. Ratify the Director of Public Works to sign Contract Change Order Number 2 for the total amount of $15,445.70 for Post Mile 5.10;
3. Ratify the Director of Public Works to sign Contract Change Order Number 3 for the total amount of $7,168.46 for Post Mile 5.10;
4. Ratify the Director of Public Works to sign Contract Change Order Number 2-S1 for the total amount of $29,281.27 for Post Mile 9.00;
5. Ratify the Director of Public Works to sign Contract Change Order Number 1-S1 for the total amount of $8,604.40 for Post Mile 11.05-11.29;
6. Accept the completed contracts, including all change orders approved by the Public Works Department, between William J. Etter Construction and Humboldt County for construction of Storm Damage Repair to Mattole Road (F3D010) Post Miles 4.40, 5.10, 9.00, and 11.05-11.29; and
7. Approve the final claims for payment, as submitted by the Public Works Department to the Auditor/Controller, in the amounts of $20,850.90 for Mattole Road (F3D010) Post Mile 4.40, $22,626.78 for Mattole Road (F3D010) Post Mile 5.10, $29,440.00 for Mattole Road (F3D010) Post Mile 9.00, and $8,604.40 for Mattole Road (F3D010) Post Mile 11.05-11.29, which will bring the total amounts paid to 100 percent of the contracts.
Body
SOURCE OF FUNDING:
Road Fund (1200); Federal Highway Administration Emergency Relief Funds
DISCUSSION:
On Mar. 7, 2017, the Governor of the State of California declared a disaster for Humboldt County due to severe winter storms, flooding, and mudslides. Mattole Road (F3D010) Post Miles 4.40, 5.10, 9.00, and 11.05-...