File #: 26-47    Version: 1 Name:
Type: Informational Report Status: Consent Agenda
File created: 1/9/2026 In control: Public Works
On agenda: 2/3/2026 Final action:
Title: Accept Completed Contract for Public Works Measure - O 2025 Road Maintenance Project Jacoby Creek and South Quarry Road
Strategic Framework: 9999 - Core Services / Other
Attachments: 1. Staff Report, 2. Executed Project Agreement and Change Order, 3. Acceptance Statement
Previous Action/Referral: 25-968, 25-881

To: Board of Supervisors

From: Public Works

Agenda Section: Consent

Vote Requirement: Majority

SUBJECT:
title
Accept Completed Contract for Public Works Measure - O 2025 Road Maintenance Project Jacoby Creek and South Quarry Road

end

RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Accept the completed contract, including all approved change orders, with Kernen Construction, regarding the construction of Public Works Measure O - 2025 Road Maintenance Project Jacoby Creek and South Quarry Road; and
2. Approve the final claim for payment, to be submitted by the Department of Public Works to the Auditor-Controller's Office, in the amount of $250, which will bring the total amount paid to 100% of the contract; and
3. Direct the Clerk of the Board to provide the Roads Division of the Department of Public Works with one fully executed certified copy of the Board order related to this item.

Body
STRATEGIC PLAN:
The recommended actions support the following areas of the Board of Supervisors' Strategic Plan:

Area of Focus: Core Services/Other
Strategic Plan Category: 9999 - Core Services/Other

DISCUSSION:
The Public Works Measure O - 2025 Project consists Hot Mix Asphalt overlay road surface. These locations are Jacoby Creek Road and South Quarry Road.

On July 22, 2025, the Humboldt County Board of Supervisors ("Board") authorized the Clerk of the Board to advertise the Public Works Measure O - 2025 Road Maintenance project Jacoby Creek and South Quarry Road project for bids. On Aug. 5, 2025, the County of Humboldt received five bids for the project. On Aug. 19, 2025, the Board awarded the project agreement to Kernen Construction, the lowest responsive bidder. The award amount was $865,131. Contract change orders executed during the project increased the authorized amount by $54,151.17. This increase is associated with the decision to add additional shoulder backing. A hot mix asphalt Curb item was also added to protect the int...