To: Board of Supervisors
From: Public Works
Agenda Section: Consent
Vote Requirement: Majority
SUBJECT:
title
Storm Damage Repair to Alderpoint Road (F6B165) Post Miles 7.90 and 8.15
end
RECOMMENDATION(S):
Recommendation
That the Board of Supervisors:
1. Approve the attached plans and specifications for the Alderpoint Road (F6B165) Post Mile 7.90 and 8.15 Storm Damage Repair Project; and
2. Find that the Alderpoint Road (F6B165) Post Mile 7.90 and 8.15 Storm Damage Repair Project is exempt from environmental review under the California Environmental Quality Act pursuant to Sections 15269(a) and 15302 of Title 14 of the California Code of Regulations; and
3. Direct the Clerk of the Board to advertise the Alderpoint Road (F6B165) Post Mile 7.90 and 8.15 Storm Damage Repair Project as required by Section 22037 of the California Public Contract Code, with bids to be opened on Tuesday, June 16, 2026, at 2:00 p.m.
Body
STRATEGIC PLAN:
The recommended actions support the following areas of the Board of Supervisors’ Strategic Plan:
Area of Focus: Core Services/Other
Strategic Plan Category: 9999 - Core Services/Other
DISCUSSION:
On Jan. 23, 2017, the Governor of the State of California declared a disaster for Humboldt County due to severe winter storms, flooding and mudslides. Alderpoint Road (F6B165) Post Miles 7.90 and 8.15, located east of the community of Garberville, experienced roadway damage.
On Jan. 22, 2019, the Humboldt County Department of Public Works (“Public Works”) received Federal Highway Administration (“FHWA”) funding approval to proceed with the Storm Damage Repairs Project. Public Works subsequently prepared the attached plans and specifications for the project based on topographic surveys of the damaged areas prepared by Points West Surveying Company and geotechnical studies prepared by Crawford and Associates.
On Sept. 24, 2019, Public Works received FHWA approval to proceed with construction. The work proposed in the attached plans and specifications at post mile 7.90 consists of constructing a temporary detour, excavating and installing a welded wire wall, placement of an underdrain, installing guardrail, reconstruction of the roadway, and implementation of erosion control measures. At post mile 8.15 the work consists of constructing a temporary detour, excavation and backfill for geosynthetic reinforced embankment, installing sub-surface permeable drainage blanket, constructing surface drainage system and implementation of erosion control measures.
The Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project involves the replacement and reconstruction of existing road infrastructure in the same location as it existed prior to suffering damage and is within the scope of the disaster declaration made by the Governor of California on Jan. 23, 2017. Such work is considered exempt from environmental review under the California Environmental Quality Act pursuant to Sections 15269(a) and 15302 of Title 14 of the California Code of Regulations.
Accordingly, Public Works recommends that the Board of Supervisors approve the attached plans and specifications for the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project; find the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project is exempt from environmental review under the California Environmental Quality Act pursuant to Sections 15269(a) and 15302 of Title 14 of the California Code of Regulations; and direct the Clerk of the Board to advertise the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project as required by Section 22037 of the California Public Contract Code, with bids to be opened on Tuesday, June 16, 2026, at 2:00 p.m.
SOURCE OF FUNDING:
Humboldt County Road Fund - Measure O (1200-321); Federal Highway Administration Emergency Relief, California Governor’s Office of Emergency Services
FINANCIAL IMPACT:
|
Expenditures (1200-321) |
FY26-27 Projected* |
|
Budgeted Expenses |
$1,191,000.00 |
|
Total Expenditures |
$1,191,000.00 |
|
Funding Sources (1200-321) |
FY26-27 Projected* |
|
Road Fund- Measure O (2.87%) |
$34,181.70 |
|
State/Federal Funds (97.13%) |
$1,156,818.30 |
|
Total Funding Sources |
$1,191,000.00 |
*Projected amounts are estimates and are subject to change.
There is no financial commitment until the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project is awarded. This project is being funded by the Federal Highway Administration Emergency Relief Fund (88.53%), California Governor’s Office of Emergency Services funding (8.60%) and the Humboldt County Road Fund - Measure O (2.87%). The engineer’s cost estimate for the project is $1,191,000. The Humboldt County Road Fund will be responsible for $34,181.70 of the costs associated with the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project. Expenditure appropriations related to completion of the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project are included in the approved fiscal year 2025-26 budget and the 2026-27 proposed budget for Roads Engineering, 1200-321.
Humboldt County adopted county-wide local transactions and use tax (sales tax) through an affirmative vote on a local measure known as Measure O. Public Works will use Measure O funds for the grant match portion of the project.
STAFFING IMPACT:
The recommended actions will not impact current staffing levels.
OTHER AGENCY INVOLVEMENT:
Federal Emergency Management Agency; California Governor’s Office of Emergency Services
ALTERNATIVES TO STAFF RECOMMENDATIONS:
The Board of Supervisors may choose not to approve the attached plans and specifications for the Alderpoint Road (F6B165) Post Miles 7.90 and 8.15 Storm Damage Repair Project. However, this alternative is not recommended since the project will restore the roadway to pre-disaster conditions using funds that would not otherwise be available to the County of Humboldt.
ATTACHMENTS:
1. Plans for Alderpoint Road (F6B165) Post Miles 7.90 and 8.15
2. Special Provisions for Alderpoint Road (F6B165) Post Miles 7.90 and 8.15
3. Notice to Bidders for Alderpoint Road (F6B165) Post Miles 7.90 and 8.15
PREVIOUS ACTION/REFERRAL:
Meeting of: None
File No.: None