Title: Appropriation Transfer to Establish Equipment (8986) Fixed Asset Line for the Roads-Maintenance budget 1200325, in the amount of $19,292 (4/5 Vote Required)
Attachments: 1. Staff Report, 2. Appropriation Transfer 1200325.pdf

 

To:                                                               Board of Supervisors

 

From:                                          Public Works                                          

 

Agenda Section:                     Consent                     

 

Vote Requirement:                     4/5th

 

SUBJECT:

title

Appropriation Transfer to Establish Equipment (8986) Fixed Asset Line for the Roads-Maintenance budget 1200325, in the amount of $19,292 (4/5 Vote Required)

end

 

RECOMMENDATION(S):

Recommendation

That the Board of Supervisors

1. Approve the appropriation transfer (Attachment 1) in fiscal year (FY) 2026-27 for the purchase of one (1) Mobile Steel Office Box estimated at $19,292 in the Roads-Maintenance budget, 1200325 (4/5 Vote Required); and

2. Authorize the Auditor-Controller to establish fixed asset line 8986, Equipment, in the Roads-Maintenance budget, 1200325, for FY 2026-27; and

3. Request Clerk of the Board to send a certified board order to the Purchasing department.

Body

 

STRATEGIC PLAN:

This action supports the following areas of your Board’s Strategic Plan.

 

Area of Focus:  Workforce & Operational Excellence                     

Strategic Plan Category:  9999 - Core Services/Other

 

DISCUSSION:

The Roads Department requests to purchase one (1) Mobile Steel Mobile Box for the Rock Crusher Crew. The mobile office is necessary to support Mine Safety and Health Administration (MSHA) regulated rock crushing and/or mining operations by providing a secure on-site facility for required safety and training records, workplace documentation, employee training, first-aid materials, and operational coordination at remote mining locations. The previous mobile office was integrated into the generator set that powered the former cone and jaw crusher equipment. The replacement of the crusher equipment resulted in the loss of the crew’s on-site office facility.

 

SOURCE OF FUNDING: 

Road Fund (1200)

 

FINANCIAL IMPACT:

Expenditures- Adopted (1200325)

FY26-27

Budgeted Expenses

 $19,292

Total Expenditures

 $19,292

Funding Sources- Adopted (1200325)

FY26-27

Fees/Other

$19,292

*Projected amounts are estimates and are subject to change.

 

Narrative Explanation of Financial Impact:

This item recommends transferring funds from the Services and Supplies category, to the appropriate Fixed Asset line, Equipment 8986, for FY 2026 - 27 in the Roads-Maintenance budget, 1200325. There are no changes to the overall Roads-Maintenance budget, 1200325.

 

STAFFING IMPACT:

There will be no impact to staffing.

 

OTHER AGENCY INVOLVEMENT:

N/A

 

ALTERNATIVES TO STAFF RECOMMENDATIONS:

Your Board could choose not to approve the purchase of a mobile steel office box. However, this is not recommended as it would result in inadequate on-site weather-resistant facilities for maintaining required mine safety documentation, conducting safety briefings, and supporting the crushing operations. This could increase the risk of non-compliance findings during MSHA inspections and reduce operational efficiency.

 