File #: 22-395    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 3/28/2022 In control: Public Works
On agenda: 4/19/2022 Final action: 4/19/2022
Title: Accept Completed Contract for Storm Damage Repairs to Alderpoint Road (F6B165) Post Mile 0.22
Attachments: 1. Staff Report, 2. Contract Change Order Number 1 – Supplement Number 1, 3. Executed Project Agreement and Contract Change Orders, 4. Acceptance Statement

 

To:                                                               Board of Supervisors

 

From:                                          Public Works                                          

 

Agenda Section:                     Consent                                                               

 

SUBJECT:

title

Accept Completed Contract for Storm Damage Repairs to Alderpoint Road (F6B165) Post Mile 0.22

end

 

RECOMMENDATION(S):

Recommendation

That the Board of Supervisors:

1.                     Ratify the Director of Public Works to sign Contract Change Order Number 1 - Supplement Number 1 for the total amount of $13,350;

2.                     Accept the completed contract, including all change orders approved by the Public Works Department, between Bouthillier’s Construction, Inc., and Humboldt County for construction of Alderpoint Road (F6B165) Post Mile 0.22 Storm Damage Repair Project; and

3.                     Approve the final claim for payment, to be submitted by the Public Works Department to the Auditor/Controller, in the amount of $19,265, which will bring the total amount paid to 100% of the contract.

 

Body

SOURCE OF FUNDING                     

Road Fund (1200); Federal Highway Administration Emergency Relief Funds

 

DISCUSSION:

On Feb. 21, 2019, the Governor of the State of California declared a disaster for Humboldt County due to severe winter storms, flooding, and mudslides.  Alderpoint Road (6B165) Post Mile 0.22, in the Garberville area of southern Humboldt County, experienced an embankment failure that closed the eastbound lane of the roadway. This lane remained closed until the restoration project was completed.

 

On Oct. 10, 2019, the Humboldt County Department of Public Works (“Public Works”) received Federal Highway Administration funding approval to proceed with the Alderpoint Road (6B165) Post Mile 0.22 Storm Damage Repair Project.  Mark Thomas and Company subsequently prepared plans and specifications for the project based on a topographic survey of the damaged area prepared by Points West Surveying Company and a geotechnical study prepared by Crawford and Associates.   The work consisted of constructing a soldier pile wall and drainage features, reconstructing the roadway to original width, installing a guardrail, and adding sediment and erosion control items.

 

On Nov. 5, 2019, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise the Alderpoint Road (F6B165) Post Mile 0.22 Storm Damage Repair Project for bids.  On Dec. 17, 2019, the County of Humboldt received nine (9) bids for the project. The project agreement was awarded to Bouthillier’s Construction, Inc., the lowest responsible bidder, on Jan. 14, 2020. The award amount was $789,065, and contract change orders executed during the project increased the authorized amount by $81,631.35.

 

Public Works recommends that the Board of Supervisors ratify the Director of Public Works to sign Contract Change Order Number 1 - Supplement Number 1; accept the completed contract, including all change orders approved by Public Works for this project; and approve the final claim for payment.

 

FINANCIAL IMPACT:

Total construction costs for this project are $870,696.35. Progress payments totaling $851,431.35 have been paid, and the final claim for payment in the amount of $19,265 is outstanding. This project is funded by Federal Highway Administration (FHWA) Emergency Relief Funds (88.53%) and the Humboldt County Road Fund (11.47%). Expenditure appropriations relating to completion of the Alderpoint Road (F6B165) Post Mile 0.22 Storm Damage Repair Project are included in the approved Fiscal Year 2021-22 Road Fund Budget (1200321-2118).

 

Projects are paid in arrears with anticipated funding coming from FHWA as mentioned above. The FY 2020-21 Annual Road Report, completed by the State of California, reflected an estimated negative fund balance of $5.9 million. This negative balance is due to the timing of Federal Emergency Management Agency (FEMA) reimbursements to the county, which can take years for the county to receive repayment. The department utilizes other state and local funding, such as Regional Surface Transportation Program funds, for the 11.47% Humboldt County Road Fund match for FHWA projects.

 

STRATEGIC FRAMEWORK:

This action supports your Board’s Strategic Framework by providing for and maintaining infrastructure .

 

OTHER AGENCY INVOLVEMENT:                     

California Department of Transportation, Federal Highway Administration

 

ALTERNATIVES TO STAFF RECOMMENDATIONS:                     

The Board of Supervisors may choose not to accept the Alderpoint Road (F6B165) Post Mile 0.22 Storm Damage Repair Project.  However, staff does not recommend this alternative because the project has been completed, and the requested Board actions are needed to accept the contract.

 

ATTACHMENTS:                     

1.                     Contract Change Order Number 1 - Supplement Number 1

2.                     Executed Project Agreement and Contract Change Orders

3.                     Acceptance Statement

 

PREVIOUS ACTION/REFERRAL:

Board Order No.: C-17 / C-11                     

Meeting of: Nov. 5, 2019 / Jan. 14, 2020

File No.: 19-1564 / 20-16