File #: 26-628    Version: 1 Name:
Type: Informational Report Status: Consent Agenda
File created: 6/9/2026 In control: Public Works
On agenda: 7/7/2026 Final action:
Title: Award Authorization for Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems
Strategic Framework: 1007 – Improve the transportation network to be multi-modal, safe, sustainable and equitable
Attachments: 1. Staff Report, 2. Bid Results for HSIP Edgelines on Indian Reservation Road Systems, 3. Construction Agreement for HSIP Edgelines on Indian Reservation Road Systems
Previous Action/Referral: 26-358

 

To: Board of Supervisors

 

From: Public Works                                          

 

Agenda Section: Consent                     

 

Vote Requirement:                     Majority

 

SUBJECT:

title

Award Authorization for Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems

end

 

RECOMMENDATION(S):

Recommendation

That the Board of Supervisors:

1.                     Receive and file the bid proposals submitted for the Edgelines on Indian Reservation Road Systems Project; and

2.                     Award the project agreement to GR Sundberg, Inc., for the total amount of $792,549.10; and

3.                     Authorize the Chair of the Board to execute the project agreement upon submittal of the appropriate bonds and insurance; and

4.                     Authorize the Director of Public Works to execute contract change orders up to the amount of $39,625.90; and

5.                     Direct the Clerk of the Board to provide the Engineering Division of the Department of Public Works with one (1) fully executed certified copy of the Board order related to this item.

 

Body

STRATEGIC PLAN:

This action supports the following areas of your Board’s Strategic Plan.

 

Area of Focus:  Safe & Healthy Communities                     

Strategic Plan Category:  1007 - Improve the transportation network to be multi-model, safe, sustainable and equitable

 

DISCUSSION:

On May 12, 2026, the Humboldt County Board of Supervisors (“Board”) authorized the Clerk of the Board to advertise the Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems Project for bids. On Jun. 9, 2026, the County of Humboldt received three (3) bids for the project, which are attached hereto as Attachment 1.

 

Accordingly, the Department of Public Works recommends that the Board: receive and file the bid proposals submitted for the Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems Project; award the project agreement to GR Sundberg, Inc., for the total amount of $792,549.10; authorize the Chair of the Board to execute the project agreement upon submittal of the appropriate bonds and insurance; and authorize the Director of Public Works to execute contract change orders up to the amount of $39,625.90.

 

SOURCE OF FUNDING: 

Humboldt County Road Fund - Measure O (1200-321); California Department of Transportation’s Highway Safety Improvement Program; Hoopa Valley Tribe; Karuk Tribe; and Yurok Tribe

 

FINANCIAL IMPACT:

Expenditures (1200-321)

FY26-27

Budgeted Expenses

 $911,430

Additional Appropriation Requested

 $0

Total Expenditures

 $911,430

 

Funding Sources (1200-888)

FY26-27

State Funds (HSIP)

 $820,287

Hoopa Valley Tribe (2.22%)

 $20,234

Karuk Tribe (0.86%)

 $7,838

Yurok Tribe (0.03%)

 $273

Measure O (1200-342, 6.89%)

 $62,798

Total Funding Sources

 $911,430

 

Narrative Explanation of Financial Impact:

The Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems Project is funded by the California Department of Transportation’s Highway Safety Improvement Program (90%), with the grant match being shared by the Humboldt County Road Fund - Measure O (6.89%), Hoopa Valley Tribe (2.22%), Karuk Tribe (0.86%), and Yurok Tribe (0.03%). The total project cost is estimated at $911,430.00, as shown in Attachment 1.

 

Expenditure appropriations relating to completion of the Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems Project are included in the approved fiscal year 2026-27 budget for budget unit 1200-321.

 

STAFFING IMPACT:

 

Narrative Explanation of Staffing Impact:

The recommended actions will not impact current staffing levels.

 

OTHER AGENCY INVOLVEMENT:

California Department of Transportation, Hoopa Valley Tribe, Karuk Tribe, and Yurok Tribe

 

ALTERNATIVES TO STAFF RECOMMENDATIONS:

The Board of Supervisors may choose not to award the project agreement for the Highway Safety Improvement Program Edgelines on Indian Reservation Road Systems Project. However, this alternative is not recommended because the project will improve the safety of several roadways using funds that would not otherwise be available to the County of Humboldt, Hoopa Valley Tribe, Karuk Tribe, and Yurok Tribe.

 

ATTACHMENTS:

1.                     Bid Results for HSIP Edgelines on Indian Reservation Road Systems

2.                     Construction Agreement for HSIP Edgelines on Indian Reservation Road Systems

 

PREVIOUS ACTION/REFERRAL:

Meeting of: 5/12/26

File No.: 26-358