File #: 23-369    Version: 1 Name:
Type: Informational Report Status: Passed
File created: 3/15/2023 In control: Public Works
On agenda: 4/4/2023 Final action: 4/4/2023
Title: Bid Award Authorization for the Humboldt Bay Trail South Project
Attachments: 1. Staff Report, 2. Bid Results for the Humboldt Bay Trail South Project, 3. Construction Agreement for the Humboldt Bay Trail South Project, 4. Signed Construction Agreement.pdf
Previous Action/Referral: 23-16, 22-1482, 18-941, 23-396

 

To:                                                               Board of Supervisors

 

From:                                          Public Works                                          

 

Agenda Section:                     Consent                     

 

Vote Requirement:                     Majority                                          

 

SUBJECT:

title

Bid Award Authorization for the Humboldt Bay Trail South Project

end

 

RECOMMENDATION(S):

Recommendation

That the Board of Supervisors:

1.                     Receive and file the bid proposals submitted for the Humboldt Bay Trail South Project;

2.                     Award the project agreement to McCullough Construction, Inc., for the total amount of $12,983,350.96; and

3.                     Authorize the Chair of the Board to execute the project agreement upon submittal of the appropriate bonds and insurance; and

4.                     Authorize the Public Works Director to execute contract change orders up to the amount of $210,000.

 

Body

SOURCE OF FUNDING                     

Bicycles & Trailways Program (1710), California Active Transportation Program, California

Coastal Conservancy, California Department of Transportation

 

DISCUSSION:

On Jan. 24, 2023, the Humboldt County Board of Supervisors authorized the Clerk of the Board to advertise the Humboldt Bay Trail South Project for bids. On March 14, 2023, the County of Humboldt received three (3) bids for the project, which are attached hereto as Attachment 1.

 

The Department of Public Works recommends that the Board of Supervisors: receive and file the bid proposals submitted for the Humboldt Bay Trail South Project; award the attached project agreement to McCullough Construction, Inc., for the total amount of $12,983,350.96; authorize the Chair of the Board to execute the attached project agreement upon submittal of the appropriate bonds and insurance; and authorize the Public Works Director to execute contract change orders up to the amount of $210,000.

 

FINANCIAL IMPACT:

Expenditures (Fund, Budget Unit)

FY22-23 Adopted

FY23-24 Projected

FY24-25 Projected

Budgeted Expenses (1710)

 $1,629,600.00

 $9,777,600.00

 $4,888,800.00

Additional Appropriation Requested

 $0

 $0

 $0

Total Expenditures

 $1,629,600.00

 $9,777,600.00

 $4,888,800.00

Funding Sources (Fund, Budget Unit)

FY22-23 Adopted

FY23-24 Projected*

FY24-25 Projected*

State/Federal Funds (ATP)

 $1,321,935.76

 $7,931,614.56

 $3,965,807.28

State Funds (Caltrans)

 $122,088.98

 $732,533.90

 $366,266.95

State Funds (Coastal Conservancy)

 $185,575.26

 $1,113,451.54

 $556,725.77

Total Funding Sources

 $1,629,600.00

 $9,777,600.00

 $4,888,800.00

*Projected amounts are estimates and are subject to change.

 

Narrative Explanation of Financial Impact:

Construction of the Humboldt Bay Trail South Project is being funded by the California Transportation Commission’s Active Transportation Program (up to $13,300,000), the California Department of Transportation’s Minor B Program (up to $1,250,000), and the California Coastal Conservancy (up to $1,900,000). The total available funding from these sources is $16,450,000, and the total project cost for construction and construction engineering is estimated at $16,296,000. Therefore, the County of Humboldt will not be responsible for any of the costs associated with constructing the Humboldt Bay Trail South Project.

 

Expenditure appropriations relating to completion of the Humboldt Bay Trail South Project are included in the approved fiscal year 2022-23 budget at revenue line 1710715-523190 and expenditure line 1710715-8946, and will be included in the proposed budget submittals for fiscal years 2023-24 and 2024-25. This is a reimbursement project and expenditures must be realized before any funds can be recouped. Fund 1710- Forest Resources and Recreation does not currently have dedicated revenue sources to support having cash on hand for initial project related expenditures prior to reimbursement so there is limited liability to the General Fund until reimbursement is received.

 

In future years development of the McKay Community Forest, currently under development, should generate stable revenue for the Forest Resources and Recreation Fund to mitigate that initial liability to the General Fund. Funding sources for this Humboldt Bay Trail South Project can be billed at minimum quarterly, or more often as needed when larger expenditures occur to manage cash flow coming back to the fund.

 

STRATEGIC FRAMEWORK:

This action supports your Board’s Strategic Framework priorities of creating opportunities for improved safety and health and providing for and maintaining infrastructure.

 

OTHER AGENCY INVOLVEMENT:                     

California Transportation Commission, California Department of Transportation, California Coastal Conservancy

 

ALTERNATIVES TO STAFF RECOMMENDATIONS:                     

The Board of Supervisors may choose not to award the project agreement for the Humboldt Bay Trail South Project. However, this alternative is not recommended because the project will construct the final segment of the Humboldt Bay Trail, a regional priority for over 20 years, using funds that would not otherwise be available to Humboldt County.

 

ATTACHMENTS:                     

1.                     Bid Results for the Humboldt Bay Trail South Project

2.                     Construction Agreement for the Humboldt Bay Trail South Project

 

PREVIOUS ACTION/REFERRAL:

Board Order No.: C-1 / D-22 / D-16                     

Meeting of: July 31, 2018 / Nov. 8, 2022 / Jan. 24, 2023

File No.: 18-941 / 22-1482 / 23-16